9/25/2023 0 Comments Pom qm crashingPessimistic Estimate 12 weeks 39 weeks 18 weeks 36 weeks 24 weeks 14 weeksĪ) Find the estimate of the mean and variance of the duration of each activity. Most Likely Estimate 12 weeks 21 weeks 15 weeks 27 weeks 18 weeks 5 weeks Optimistic Estimate 12 weeks 15 weeks 12 weeks 18 weeks 12 weeks 2 weeks Using the PERT three-estimate approach, Sharon has obtained the following estimates of the duration of each activity. Considering the order in which these activities need to occur, she also has constructed the following project network table. Sharon has identified the six activities (labeled A, B. She wants the project completed within 57 weeks in time to launch the advertising campaign at the beginning of the Christmas season. Case PERT/CPM Sharon Lowe, vice president for marketing for the Electronic Toys Company, is about to begin a project to design an advertising campaign for a new line of toys.